Factory Built Building Installation Permit - Tab
FACTORY BUILT BUILDING INSTALLATION PERMIT
The Factory Built Building Installation Permit may be issued through the Department or by the local authority having jurisdiction. To determine if an installation is in a jurisdiction that has an Inspection Service Agreement (ISA), select the link below:
Jurisdictions with and without an ISA
THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO APPLYING FOR THE FACTORY BUILT BUILDING INSTALLATION PERMIT:
- Factory built building installation plan approval must be submitted and approved from the Department. Visit our Plan Review page for process and fee information.
- A licensed Installer and/or Contractor with a valid license and the appropriate license classification to perform all work related to the installation, which includes utility connections and all attached accessory structures is required. Select the link below for a list of licensees and license classification descriptions:
Arizona Department of Housing Installer
ADOH Installer License Classification Description
Registrar of Contractor
ROC license classification description
FACTORY BUILT BUILDING INSTALLATION PERMIT APPLICATION SUBMITTAL INSTRUCTIONS
Factory Built Building Installation Permit Application may be submitted by mail or over the counter. Below are links with instructions for submitting the Permit Application:
To submit online:
Permit Applications can be submitted through the online e-Licensing solution.
To submit by mail or over the counter select the following form and instructions:
The Manufactured Housing & Building Division is no longer accepting applications by mail or over the counter.
The Department shall issue or deny a permit within seven business days from the date the application is received in accordance with R4-34-801.B.
Factory Built Building Installation Permit must be displayed in a conspicuous location on the building.
PERMIT EXPIRES 6 MONTHS FROM THE DATE OF ISSUANCE
All permits, except special use permits expire 6 months from the date the permit is issued. Extension request must be received by the Department prior to the expiration date. Below are the links with instructions for completing and submitting request form:
Application for Six Month Extension on Installation Permit
Instructions for requesting an extension on Installation Permit
SCHEDULING INSTALLATION INSPECTION INSTRUCTIONS
Once the permit has been issued from the Department, inspections are required to ensure the installation meets safety and code requirements. Below is the link with instructions for scheduling inspection:
Instructions for Scheduling Inspection
MAKING CHANGES OR MODIFICATIONS TO AN EXISTING INSTALLATION PERMIT
To make a change or modification to an existing permit, the applicant can log into their e-Licensing portal account, perform the necessary changes, and pay the administrative function fee per item changed.
Refer to Fee Schedule for Administrative Function Fee cost per item.